Pole Barn 2: framing and roofing


We got about 6 inches of rain in 2 hours over the weekend, 
and this is all we have to show for it! That's a very GOOD thing.
July 1

Randy put up top rim boards by himself with some bungee cords.

My Uncle Chris and Aunt Doris came from 
Rochester for a couple days to help!
Putting up wall purlins.
July 16

We were short 2 trusses, so Chris and Doris 
helped us build 2 trusses! (We knew we would be short.
 No one walked off with 2 roof trusses.)

Wall purlins up.

July 17
Bob and his tractor, a pipe, and 2 pieces of bent rebar make a great crane!
Setting trusses with Bob, Uncle Chris, Randy, and our friend Vlad.

Vlad and Randy adding angle supports.

Barn-raising work day! Adding roof purlins.
July 21

Randy finished the last few purlins that evening. 

The friends from whom we bought the land had some
used windows they needed to unload, so 
now we have nice big windows for the shop!
Stacked on the right.

Another Sunday evening family time, with bigger fires.
July 22

Roof tin is going on! July 23

The dirt is too high. July 26

Teddy getting creative while Daddy works a skidsteer.

 Burgers for a picnic supper!

Another good day to add tin. July 27

All the area is covered where heat/insulation will be!
Aug 2