Pole Barn 3: floor prep


Installing vertical 2" foam pieces around the perimeter, 16" deep
Aug 14

It looks like Andrew did the roughed-in plumbing. 
(We hired a friend) Aug 15

Here's the dividing wall between heated/insulated 
shop/living-quarters and cold storage.

Randy leveling/smoothing the sand-gravel and laying 
that pile of 2" 4x8 under-slab insulating foam Aug 20

On a beautiful morning we all helped install PEX tubing for the in-floor heat!
The gray pipes on the right are the entrances/exits for the PEX tubing.
Aug 22

Here's our road map Randy and I drew up the night before.
 3 loops of ~275' each. Each loop meanders throughout 
the whole floor, and none of them can cross.
It would have been a frustrating morning without the map.

First "loop" is in! 

Randy and Teddy installing the 3rd loop to fill in the gaps

Bridget "overseeing"

3 loops in

Next goes wire reinforcing mesh on top of the tubing.
We have good helpers!

A professional team.

Ready for concrete!

Comments

  1. Your kids at the worksite reminds me of you and your siblings when your parents' house was being built years ago!

    ReplyDelete

Post a Comment

Popular posts from this blog

December: mud, mud, mud. Let's go skating.

August: Upper walls, ROOF! Class 5.

Cabinets 1